Assign task priorities

This is an advanced administration task.


As a splunk administrator monitoring a large environment, you can prioritize and deprioritize the execution of different tasks by the scheduler during data collection.

There are times when the collection of certain data types is of the highest priority and you want to ensure that you can collect the complete data set. You also want to collect the data with minimal impact on the resources in your environment.


You can control which data collection nodes receive resource intensive tasks so that you can adjust the resources of just those machines. For example, if you have a memory intensive task, then you want to direct that task to run on data collection nodes that you have provisioned with more memory than other data collection nodes in your environment.

You can change how data is collected by manually editing the configuration files. The configuration files used to monitor task execution are hydra_node.conf and ta_vmware_collection.conf on the scheduler node.

Set task priorities

The file ta_vmware_collection.conf contains the field, <task>_priority=value. The value that you assign to this field is used to determine the priority number for jobs of the given task. The tasks that have a priority assigned to them now have a relative priority assigned that places them at a higher or lower level over other tasks in the job queue. You can assign 0, a negative number, or a positive number as a values to this field.

  • 0 (the default value) implies that there is no change in default data collection priorities for tasks.
  • A negative value increases the job priority. A negative value lowers the priority number but this increases the actual relative priority of a given task. Jobs are worked on in ascending order of priority number, that is “1” is higher priority than “5”.
  • A positive value decreases the job priority. A positive value increases the priority number but this lowers the actual relative priority of a given task. Note that a positive priority adjustment almost always results in job expirations except in environments that are underloaded.

In ta_vmware_collection.conf all of the tasks are listed.

#These are all the tasks that should run everywhere
task = hostvmperf, otherperf, hierarchyinv, hostinv, vminv, clusterinv, datastoreinv, rpinv, task, event

You can assign a priority to each of the tasks using the custom field <task>_priority.

# The number to add to the priority number for jobs of a given task, negative number makes higher priority
task_priority = -60
event_priority = -60
hierarchyinv_priority = -120

To assign a priority to a task:

  1. Edit $SPLUNK_HOME/etc/apps/local/ta_vmware_collection.conf on the scheduler node (typically on the search head).
  2. Add the <task>_priority field(s) for the specific task(s) and assign a value to the field. The value can be 0 (no change), a negative number (increase job priority), or a positive number (decrease job priority).

  3. Restart Splunk.
  4. Restart the scheduler.

Example

Assign the following values to task, event, and hierarchyinv in ta_vmware_collection.conf

task_priority = -60

event_priority = -60

hierarchyinv_priority = -120

Unix epoch time is used to determine the priority number for tasks. For example, if epoch is currently 188, using the values assigned to <task>_priority above for task_priority and 
hierarchyinv_priority, hierarchyinv events have a priority of 68 (Unix epoch time less the value assigned to task_priority) and task events have a priority of 128. hierarchyinv is always collected before task events are collected.


How jobs are assigned

The scheduler sets the capabilities of the workers on the respective data collection nodes. Jobs are only assigned to nodes that have the capability of running those jobs, as defined in hydra_node.conf (on the scheduling node). Tasks that have a task (priority) weight of 0 (can not be executed by a data collection node) are flagged as error and all jobs relating to that task are ignored. Ready jobs are sorted based on their task weighting. Jobs are load balanced and the capabilities of the assigned jobs are checked to ensure that jobs are distributed to optimize resources and to avoid overloading any one data collect node. If the environment is unbalanced, you get a warning indicating that the capabilities have caused an uneven load across the data collection nodes.

Last modified on 04 April, 2014
How to limit data collection   Set capabilities

This documentation applies to the following versions of Splunk® App for VMware (Legacy): 3.0.2


Was this topic useful?







You must be logged into splunk.com in order to post comments. Log in now.

Please try to keep this discussion focused on the content covered in this documentation topic. If you have a more general question about Splunk functionality or are experiencing a difficulty with Splunk, consider posting a question to Splunkbase Answers.

0 out of 1000 Characters